PHOTOS: Work continues on new Interstate 74 Bridge
From the New I-74 bridge construction: Hundreds of images series
Work continues around the anchors for the arches on the new Interstate 74 bridge Tuesday, April 2, 2019. Milling and painting of the westbound arch is complete with plans to install the first segments in the coming weeks. The predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new Interstate 74 Bridge.

Work continues around the anchors for the arches on the new Interstate 74 bridge Tuesday. The predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design," which will rise 164 feet above both spans of the new I-74 bridge. The first pieces of arch were in place this week on three out of the four anchors.

Work continues around the anchors for the arches on the new Interstate 74 bridge Tuesday. Milling and painting of the westbound arch is complete with plans to install the first segments in the coming weeks. The predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I-74 bridge.

Iron workers tie rebar for the eastbound arch piers for the new I 74 Interstate Bridge Tuesday, April 2, 2019.

Work continues around the anchors for the arches on the new Interstate 74 bridge Tuesday, April 2, 2019. Milling and painting of the westbound arch is complete with plans to install the first segments in the coming weeks. The predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I74 bridge.

The green towers at left were raised to help accommodate the construction of the arches on the new Interstate 74 bridge. Three out of four of the first pieces of arch are in place on their anchors, but floodwater could slow progress.

Plans are to begin installation of the first segments of the westbound arch in the coming weeks, however, the predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I74 bridge.

Work continues around the anchors for the arches on the new Interstate 74 bridge Tuesday, April 2, 2019. Milling and painting of the westbound arch is complete with plans to install the first segments in the coming weeks. The predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I74 bridge.

Work continues around the anchors for the arches on the new Interstate 74 bridge Tuesday, April 2, 2019. Milling and painting of the westbound arch is complete with plans to install the first segments in the coming weeks. The predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I74 bridge.

Workers have completed milling and painting of the westbound arch piers on the Illinois side of the river. The plan is to install the first segments in the coming weeks, however, the predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I74 bridge.

Workers have completed milling and painting of the westbound arch piers on the Illinois side of the river. The plan is to install the first segments in the coming weeks, however, the predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I74 bridge.

Workers have completed milling and painting of the westbound arch piers on the Illinois side of the river. The plan is to install the first segments in the coming weeks, however, the predicted higher flood levels on the Mississippi River may impact progress on the main feature of the "basket-handle design" which will rise 164 feet above both spans of the new I74 bridge.